Community Health Center of Southeast Kansas

Community Health Center of Southeast Kansas

The clinic was partially funded by the USDA which had several requirements and additional paperwork associated. We had monthly construction meetings with a representative of USDA office and everything went very smoothly. The project was completed on time and in budget. The only Change Orders were ones the Owner initiated. The Owner had a very tight dead-line to get moved into this facility as they had a hard deadline to move out of their existing building they were leaving. This facility had medical, dental and behavioral health spaces within it.

Challenge:

Keeping the design and construction time frame.

Solution:

There were no time extensions on the project and they moved into their new facility on time.